TSF was engaged to upgrade the backup power plant for the site.
The Casino required a 100% reliable emergency generating plant which could provide power if a mains power failure occurred. The equipment had to be capable of synchronising with Energy Australia’s grid to ensure immediate changeover between the grid and the plant if necessary.
TSF supplied and installed a solution which now provides 100% of the Casino’s maximum demand.
TSF was also contracted to upgrade the control system for the Generation plant giving the casino an N+2 rating and we have been ensuring the plant reliability since.
The final solution consisted of the following components: